Savings in running costs and reductions in CO2 emissions are the motivation behind the use of piles and ground slab for harnessing ground-source heating/cooling energy |
|
|
|
|
|
Head office of the Strabag holding company
In addition to usage as the head office of the construction holding company, shops, bars and restaurants are also located in the building. |
|
|
|
|
|
|
- |
Completion: |
|
2003 |
|
|
|
|
|
|
- |
Gross floor space: |
|
28,000 m2 |
|
|
|
|
|
|
- |
Number of floors: |
|
12 |
|
|
|
|
|
|
- |
Underground parking spaces: |
|
300 |
|
|
|
|
|
|
- |
Client: |
|
Bauholding Strabag AG Zentrale, Vienna - A |
|
|
|
|
|
|
- |
Architect: |
|
DI Ernst Hoffmann, Vienna - A |
|
|
|
|
|
|
- |
Building services consultant: |
|
Zentralplan Planungsges.m.b.H., Wiener Neustadt - A |
|
|
|
|
|
|
|
|
|
 |
enercret installation: |
|
|
|
|
|
220 steel-reinforced concrete piles DN 65 cm, length 15 m plus the ground slab with 6000 m² were equipped with approx. 78 km of HDPE piping DN 25/2.3 mm to harness and store geothermal energy for heating and cooling the building. |
|
|
|
|
|
|
- |
Cooling capacity: |
|
2,026 kW |
|
|
|
|
|
|
- |
Heating capacity: |
|
1,680 kW |
|
|
|
|
|
|
- |
Cooling output/year: |
|
1,450 MWh |
|
|
|
|
|
|
- |
Heating output/year: |
|
840 MWh |
|
|
|
|
|
|
|
 |